| PROGRAMME | Environment and Climate Action Sector Operational Programme |
| PRIORITY AREA | Waste (Infrastructure Activities) |
| BENEFICIARY(IES) | Union of Kastamonu Local Administrations (KASMİB) |
| PLACE | Kastamonu |
| ABOUT THE PROJECT | Overall Objective of the project is:
To accelerate Türkiye’s development by ensuring compliance with the relevant Turkish and EU legislation in the waste sector and by safeguarding public health and the environment in the municipalities within the Union of Kastamonu Local Administrations Specific Objectives of the Project: To provide efficient, economical and sustainable waste management services to the member municipalities of the Union of Kastamonu Local Administrations, to prevent environmental pollution, and to contribute to the improvement of public health |
| COMPONENTS AND BUDGETS OF THE PROJECT | |
| CONTRACT 1 | |
| NAME OF THE CONTRACT | Kastamonu Integrated Solid Waste Management Project Technical Assistance and Consultancy Contract |
| BUDGET OF THE CONTRACT | 881,680.00 Euros |
| START DATE | 10/07/2020 |
| END DATE | Ongoing. |
| CONTRACT 2 | |
| NAME OF THE CONTRACT | Kastamonu Solid Waste Management Project Construction Works Contract |
| BUDGET OF THE CONTRACT | 4,179,000.00 Euros |
| START DATE | 27/07/2020 |
| END DATE | 24/11/2022 Final Acceptance Date |
| PHYSICAL PROGRESS | 100% |
| CONTRACT 3 | |
| NAME OF THE CONTRACT | Kastamonu Solid Waste Management Project Equipment Supply Contract (Lot-5) |
| BUDGET OF THE CONTRACT | 228,000.00 Euros |
| START DATE | 27/07/2023 |
| END DATE | 24/02/2025 |
| PHYSICAL PROGRESS | 100% |
| CONTRACT 4 | |
| NAME OF THE CONTRACT | Kastamonu Solid Waste Management Project Equipment Supply Contract (Lot-3,4&6) |
| BUDGET OF THE CONTRACT | 4,001,500.00 Euros |
| START DATE | 06/2024 |
| END DATE | 01/10/2024 Provisional Acceptance Date |
| PHYSICAL PROGRESS | 100% |
| CONTRACT 5 | |
| NAME OF THE CONTRACT | Kastamonu Solid Waste Management Project Equipment Supply Contract (Lot-2) |
| BUDGET OF THE CONTRACT | 774,000.00 Euros |
| START DATE | 08/06/2024 |
| END DATE | 26/12/2024 Provisional Acceptance Date |
| PHYSICAL PROGRESS | 100% |
| CONTRACT 6 | |
| NAME OF THE CONTRACT | Kastamonu Solid Waste Management Project Equipment Supply Contract (Lot-1) |
| BUDGET OF THE CONTRACT | |
| START DATE | It is in the tendering process. |
| END DATE | |
LOCATION: