| PROGRAMME | Environment and Climate Action Sector Operational Programme |
| PRIORITY AREA | Water (Infrastructure Activities) |
| BENEFICIARY(IES) | General Directorate of Samsun Water and Sewerage Administration |
| PLACE | Samsun/Çarşamba |
| ABOUT THE PROJECT | Overall Objective of the project is:
To contribute to the improvement of water quality in the region and public health, and to support the accession process by ensuring Türkiye’s compliance with environmental protection and EU wastewater sector directives Specific Objectives of the Project:
|
| PROJECT WEBSITE | http://carsambaatiksu.com/ |
| COMPONENTS AND BUDGETS OF THE PROJECT | |
| CONTRACT 1 | |
| NAME OF THE CONTRACT | Çarşamba Wastewater Project Technical Assistance and Consultancy Contract |
| BUDGET OF THE CONTRACT | 1,109,855.00 Euros |
| START DATE | 11/05/2020 |
| END DATE | Ongoing |
| CONTRACT 2 | |
| NAME OF THE CONTRACT | Çarşamba Wastewater Project Construction Works Contract |
| BUDGET OF THE CONTRACT | 8,799,000.00 Euros |
| START DATE | 20/05/2020 |
| END DATE | 19/09/2023 Provisional Acceptance Date |
| PHYSICAL PROGRESS | 100% |
KONUM: