| PROGRAMME | Environment and Climate Action Sector Operational Programme |
| PRIORITY AREA | Water (Infrastructure Activities) |
| BENEFICIARY(IES) | Diyarbakır Water and Sewerage Administration (DİSKİ) |
| PLACE | Diyarbakır, Bismil |
| ABOUT THE PROJECT | Overall Objective of the project is:
· To support the accession process by ensuring Türkiye’s compliance with environmental protection and EU wastewater sector directives.
Specific Objectives of the Project: · Improving the water quality of Dicle River via reducing pollution load caused by untreated wastewater discharge in the existing situation and contribute to improvement of public health, · Overcoming the operational problems in the sewerage system through partial replacement of the wastewater network. |
| COMPONENTS AND BUDGETS OF THE PROJECT | |
| CONTRACT 1 | |
| NAME OF THE CONTRACT | Bismil Wastewater Project Technical Assistance and Consultancy Contract |
| BUDGET OF THE CONTRACT | 1,409,202.73 Euros |
| START DATE | 15/04/2020 |
| END DATE | 14/02/2024 Final Acceptance Date |
| PHYSICAL PROGRESS | 100% |
| CONTRACT 2 | |
| NAME OF THE CONTRACT | Bismil Wastewater Treatment Plant and Wastewater Collection Project Construction Works Contract |
| BUDGET OF THE CONTRACT | 8,467,857.63 Euros |
| START DATE | 01/06/2020 |
| END DATE | 04/01/2023 Provisional Acceptance Date |
| PHYSICAL PROGRESS | 100% |
LOCATION: